Equivalent Annual Cost (EAC): Definition & Calculation
What Is the Equivalent Annual Cost (EAC)?
Equivalent annual cost (EAC) is the annual cost of owning, operating, and maintaining an asset over its entire life. Firms often use EAC for capital budgeting decisions, as it allows a company to compare the cost-effectiveness of various assets with unequal lifespans.
0:46Equivalent Annual Cost (EAC)
Understanding the Equivalent Annual Cost (EAC)
Equivalent annual cost (EAC) is used for a variety of purposes, including capital budgeting. But it is used most often to analyze two or more possible projects with different lifespans, where costs are the most relevant variable.
Other uses of EAC include calculating the optimal life of an asset, determining if leasing or purchasing an asset is the better option, determining the magnitude of which maintenance costs will impact an asset, determining the necessary cost savings to support purchasing a new asset, and determining the cost of keeping existing equipment.
The EAC calculation factors in a discount rate or the cost of capital. Cost of capital is the required return necessary to make a capital budgeting project—such as building a new factory—worthwhile. Cost of capital includes the cost of debt and the cost of equity and is used by companies internally to judge whether a capital project is worth the expenditure of resources.
Key Takeaways
- Equivalent annual cost (EAC) is the annual cost of owning, operating, and maintaining an asset over its entire life.
- EAC is often used by firms for capital budgeting decisions, as it allows a company to compare the cost-effectiveness of various assets that have unequal lifespans.
- EAC allows managers to compare the net present values of different projects over different periods, to accurately determine the best option.
The Formula for the Equivalent Annual Cost
EAC=1−(1+Discount Rate)−nAsset Price×Discount Ratewhere:Discount Rate=Return required to make projectworthwhilen=Number of periods
How to Calculate the Equivalent Annual Cost
- Take the asset price or cost and multiply it by the discount rate.
- The discount rate is also called the cost of capital, which is the required return necessary to make a capital budgeting project, such as building a new factory, worthwhile.
- In the denominator add 1 + the discount rate and raise the result as an exponent to the number of years for the project. Subtract the result by 1 and divide the numerator figure by the denominator.
- Many financial online calculators are available to calculate EAC.
Example of the Equivalent Annual Cost
As stated earlier, EAC allows managers to compare NPVs of different projects over different periods, to accurately determine the best option. Consider two alternative investments in machinery equipment:
1. Machine A has the following:
- An initial capital outlay of $105,000
- An expected lifespan of three years
- An annual maintenance expense of $11,000
2. Machine B has the following:
- An initial capital outlay of $175,000
- An expected lifespan of five years
- An annual maintenance expense of $8,500
The cost of capital for the company making the decision is thus 5%.
Next, we calculate the EAC, which is equal to the net present value (NPV) divided by the present value annuity factor or A(t,r), while taking into account the cost of capital or r, and the number of years in question or t.
The annuity factor is calculated as follows:
Annuity Factor=r1−(1+r)t1where:r=Cost of capitalt=Number of periods
Using the formula above, the annuity factor or A(t,r) of each project must be calculated. These calculations would be as follows:
Machine A, A(t, r)=.051−(1+.05)31=2.72
Machine B, A(t, r)=.051−(1+.05)51=4.33
Next, the initial costs must be divided by the annuity factor or A(t,r) while adding in the annual maintenance cost. The calculation for EAC is:
EAC Machine A=2.72$105,000+$11,000=$49,557
EAC Machine B=4.33$175,000+$8,500=$48,921
By standardizing the annual cost, a manager in charge of a capital budgeting decision where cost is the only issue would select Machine B because it has an EAC that is $636 lower than Machine A.
The Difference Between the Equivalent Annual Cost and the Whole-life Cost
Whole-life cost is the total expense of owning an asset over its entire life, from purchase to disposal, as determined by financial analysis. It is also known as a "life-cycle" cost, which includes purchase and installation, design and building costs, operating costs, maintenance, associated financing costs, depreciation, and disposal costs.
Whole-life cost also takes into account certain costs that are usually overlooked, such as those related to environmental and social impact factors.
The equivalent annual cost (EAC) is the annual cost of owning, operating, and maintaining an asset over its entire life while the whole life cost is the total cost of the asset over its entire life.
Limitations of Using the Equivalent Annual Cost
A limitation with EAC, as with many capital budgeting decisions, is that the discount rate or cost of capital must be estimated for each project. Unfortunately, the forecast can turn out to be inaccurate, or variables can change over the life of the project or life of the asset that's be considered.
Accounting
- Calculating Cost of Capital from Annual Reports: A Practical Guide
- Best Cities for Early Retirement in 2024: Cost of Living & Lifestyle
- Understanding AER: Annual Equivalent Rate Explained
- Equivalent Annual Annuity (EAA): Project Evaluation Explained
- Weighted Average Cost of Capital (WACC) Explained | Definition & Calculation
- Contribution Margin: Definition, Calculation & Importance
- Understanding Annual Premium Equivalent (APE) in UK Insurance
- High-Low Method: Cost Accounting Explained
- Average Cost Inventory Method: Definition, Calculation & Benefits
-
Understanding Allowed Depreciation: Tax Deductions for BusinessesAllowed depreciation refers to the depreciation that a business is allowed to deduct from its tax liabilities. The annual depreciation of assets needs to be considered while calculating an individual&...
-
Understanding Opportunity Cost: A Simple ExplanationYou know that feeling of hesitation when you’re deciding whether you want to order pizza or Chinese for dinner? And then, when you finally decide on pizza and the food arrives, you wish you had gotten...